Capital Projects Update: September 2018
Capital Projects Update: September 2018
Posted on 09/20/2018
Ribbon cutting at Klahowya

It's been an exciting start to the school year! We cut the ribbon on the additions at Klahowya Secondary. We also opened a significant portion of Olympic High’s rebuilt center. This allowed more of our students to start the year in permanent, modern classrooms.

We'll celebrate several milestones this year. By the end of 2019, we expect to wrap up several major construction projects. There will be a lot to keep up with, so stay tuned throughout the year to the district Facebook page or our website’s Construction Updates page!  

Klahowya Secondary

Students are taking classes in the new additions.

Status: We celebrated the opening of the addition on Sept. 19! The project gave students 13 new permanent classrooms, 3 labs, an auxiliary gym and a music room!

What's next: Landscaping and detail work on the inside will continue this fall.

Safety & Security Improvements

Overview of the Brownsville's secure entrance

Status: Security cameras were installed at Fairview Middle. We are accepting bids for secure entrance construction at Brownsville, Esquire Hills, PineCrest and Woodlands.

What's next: We will soon request bids for Cougar Valley, Hawk and Green Mountain. We continue to improve designs for Cottonwood and Fairview.

CK High & CK Middle

New CKHS stadium

Status: Middle school classrooms are taking shape! Crews are painting and installing ceiling tiles in the middle school. Framing for the high school is complete and crews are installing infrastructure. Turf was installed at the new high school stadium and Huey Field, and the new tennis courts opened for practice on the first day of school.

What's next: â€‹Crews will continue to install infrastructure and drywall in the high school, and finishes in the middle school.

 

Olympic High

Students in the new center building

Status: Students were in more permanent classrooms as a significant portion of Olympic's new center building opened. Areas open include a manufacturing lab, two CTE classrooms, band and choral classrooms, an art classroom, commons and kitchen.

What's next: Second floor counseling center and classrooms are being readied for opening later this fall.

Silverdale Elementary

Illustration of the new Silverdale wing

Status: Crews are preparing the ground behind the school for the new classroom wing. 

What's next: Building assembly will begin in early October. Classes will open later this fall.