Capital Projects Update: September 2019
Capital Projects Update: September 2019
Posted on 09/19/2019
Entrance to new CKHS

It’s exciting to see our major construction projects come to life! We opened the year with the newly built Central Kitsap High. All three high schools celebrated home football games, with fans in grandstands. 

We are keeping the major construction promises we made to our community when we asked for their support of the 2016 bond. We’ll wrap up security improvements this fall. And we’ll continue critical repairs throughout the district.

CK High

ckhs interior

Status: OPEN! Join us at 6 p.m. Oct. 2 for a grand opening celebration for both CK High and CK Middle. CK High also celebrated its first home football game on the new Cougar Field at Kitsap Credit Union Athletic Complex!

What’s Next: Crews will finish painting and other interior work on the satellite gym (the former CK Middle gym) and install bleachers at the new softball field.

Klahowya Secondary

ks field

Status: We resurfaced tennis courts. The school celebrated its first home football game with fans in the grandstands!

What’s Next: Athletics sponsor Integrity Roofing & Construction will add a roof to the grandstands.

CK Admin/Silverdale Library

Floor plan of former CKHS 900 buliding, which will house CK Admin on second floor and library on first floor
Status
: Architects have completed the design development phase, the second of three phases. A bid has been awarded to demolish the unusable portion of the old CK High.

What’s Next: Creation of construction documents begins. We expect to request construction bids in early 2020.

Safety & Security

cougar valley entrance

Status: With work over the summer, secure entrances are complete at 17 schools. 

What’s Next: Work continues on our final two schools. An addition and new entrance to Cottonwood are under construction. And entrance construction for relocation of the main office at Cougar Valley.

Olympic High

Football players in front of grandstands at Integrity Stadium
Status: Olympic celebrated its first home football game of the year at Integrity Stadium. The stadium has new accessible bleachers, and a Trojan logo on the field. The school board approved floor plans to modernize classroom and athletic wings.

What’s Next: More detailed design work begins for the second phase of modernization.

Ridgetop Middle

illustration of theater near Ridgetop's current entrance

Status: Design development, the second of three design phases, is finished. 

What’s Next: Project leaders are creating construction documents and expect to request construction bids in early 2020.